How long does it take to install a heat interface unit (HIU)?
It’s a question we get asked a lot, and the answer depends on several factors, including access and collaboration with other teams, but here’s a rough guide:
New build (pre-plumbed, first fix complete): 2 to 4 hours per unit
(If the pipework and risers are already in place, the HIU can be mounted, connected, tested and commissioned relatively quickly)
Retrofit in existing buildings: 4 to 8+ hours per unit
(Older properties may need extra time for adapting pipework, managing access or replacing legacy systems)
Complex installs (e.g. with metering, BMS integration or multiple zones):
Up to one full day per unit
(This includes flushing, commissioning and any additional controls setup)